Previous Projects
Some of pervious projects over the past few years are:
- Overhaul of MTU 8V 396 on the BP Miller
- Overhaul of CAT 3406 on the Captain FSPO
- MTU 16V 396 Overhaul for Britannia
- Top end overhaul planned maintenance on the Brent Delta platform
- Installation/commissioning of an MTU 20V 4000 series on the North Alwyn platform - North Alwyn Project
- Maintenance & repair of an MTU 12V 4000 series for Scottish & Southern Energy
BP Exploration Contract – BP Unity Platform
- Contracted to design, supply and commission 4 X 60 KVA Generator Sets. We also manufactured and installed the exhaust system as well as designing and installing the specialised sump.
- This £500,000 contract was started in 2004 and completed, successfully, on time in 2005.
TAQA Bratani Contract – Cormorant Alpha Platform
- Contract to supply & fit MTU Engines.
- Contract began with the design and modification stage in January 2006 and was successfully completed with the end of fitting stage in June 2006.
- This contract was valued at just under £300,000.